CHRIS HANI DISTRICT MUNICIPALITY

Emalahleni

Project Description: Gravelling of the Emalahleni road

Lady Frere - Mkaphusi
Chris Hani

Chris Hani

Lady Frere - QTN
Chris Hani

Chris Hani

Chris Hani

Project Overview:
Managing Consultant: Ndodana Consultants
Emerging Consultant: GM Turner Consultants
Managing Constructor: KNND Constructor
Emerging Constructor: Lathitha Construction & Services; Odwa and Soli; Nqatiko Construction; Luqaqambo Civil Construction; Ogi Yonke Construction
SHEQ Consultant:
Social Facilitator
Number of jobs created: Planned 50, jobs created to date is 29
Project phase (all projects are split into six phases): Construction (22%)
Investment/ Budget: R4 000 000
Duration: 12 Months
CDC Project Manager: Akash Singh

Ngcobo

Project Overview:
Managing Consultant:
Emerging Consultant:
Managing Constructor:
Emerging Constructor:
SHEQ Consultant:
Social Facilitator:
Number of jobs created:
Project phase (all projects are split into six phases):
Investment/ Budget:
CDC Project Manager:

Sakhisizwe

Project Overview:
Managing Consultant:
Emerging Consultant:
Managing Constructor:
Emerging Constructor:
SHEQ Consultant:
Social Facilitator:
Number of jobs created:
Project phase (all projects are split into six phases):
Investment/ Budget:
CDC Project Manager:

Tsolwana

Project Description: Road Routine Maintance(RRM)
Project Overview:
Managing Consultant: Ndodana Consultant
Emerging Consultant: Flux
Managing Constructor: KNND Constructors
Emerging Constructor: Ultramatix; Ntsikamvana; Lulonke
SHEQ Consultant:
Social Facilitator:
Number of jobs created: Planned is 70, jobs created to date is 63
Project phase (all projects are split into six phases): Construction (97%)
Investment/ Budget: Overall Budget R5 000 000
Duration: 12 Months
CDC Project Manager: Akash Singh

Intsika Yethu

Project description: Gravelling of the Intsika Yethu road

Project Overview:
Managing Consultant: Ndodana Civil Engineering
Emerging Consultant: GG&G Consultants
Managing Constructor: KNND Constructors
Emerging Constructor: Ogi Yonke; Sida Construction; Thabile Trading; Bush Clearing Construction
SHEQ Consultant:
Social Facilitator:
Number of jobs created: Planned 100, jobs created to date is 33
Project phase (all projects are split into six phases): Construction (21%)
Investment/ Budget: R4 000 000
Duration: 12 Months
CDC Project Manager: Akash Singh

Inkwanca

Project Description: Routine Road Maintenance
Project Overview:
Managing Consultant: Ndodana Consultants
Emerging Consultant: GM Turner Consultants
Managing Constructor: KNND Constructors
Emerging Constructor: Bay City Trading; Dzina Construction;
SHEQ Consultant:
Social Facilitator:
Number of jobs created: Planned is 50, jobs created to date is 10
Project phase (all projects are split into six phases): Construction (35%)
Investment/ Budget: Overall budget R3 000 000
Duration: 12 Months
CDC Project Manager: Akash Singh